Deutsche Bank AG, bauserve GmbH

Back to the projects

Project

Planning of the site logistics for the renovation of the Deutsche Bank twin-towers.

Client

Deutsche Bank AG, bauserve GmbH

Project duration

2007 - 2008

Brief description

For the renovation of the office towers, located at the city centre, a site logistics concept was required, which considered the bottleneck of small, rare free space and poor access to the buildings. Due to the very limited possibilities of a vertical transport, the site logistics had a central interface role for all assembly sections.

The present infrastructure had to be analysed and integrated into scheduled quantity structures and work flow charts. For the controlling and coordination during the construction phase, a specified manual for the operative logistics service provider was developed as a basis for the logistical processes.

Back to the projects